kV TRANSMISSION LINES EXPECTED TO BE BUILT OVER THE PERIOD FROM 2011 TO 2020



tải về 2.28 Mb.
trang11/19
Chuyển đổi dữ liệu19.08.2016
Kích2.28 Mb.
#24460
1   ...   7   8   9   10   11   12   13   14   ...   19

 

220kV TRANSMISSION LINES EXPECTED TO BE BUILT OVER THE PERIOD FROM 2011 TO 2020



No

Project name

Number of Circuits x km

Number of Circuits x kmNumber of Circuits x kmkm

Notes

 

Tranmission lines built over the period from 2011 to 2020

Tranmission lines built over the period from 2011 to 2020Tranmission lines built over the period from 2011 to 2020Tranmission lines built over the period from 2011 to 2020Tranmission lines built over the period from 2011 to 2020 

 

Northern area

 

 

 

3864

 

1

Tay Ho – splitting point Chem – Van Tri

2

x

7

14

 

2

Soc Son – Van Tri

2

x

22

44

 

3

Dong Anh – Long Bien

2

x

17

34

 

4

Dong Anh – Hiep Hoa

2

x

24

48

 

5

Splitting point Yen Phong (Bac Ninh 3) – Dong Anh – Hiep Hoa

2

x

17

34

 

6

Long Bien – Tien Son (Bac Ninh 2)

2

x

20

40

 

7

Tan Ha Noi – splitting point Ha Dong - Chem

4

x

15

60

Connected to 220kV Tay Ha Noi Substation

8

Tay Ha Noi – Hoa Binh

2

x

46

92

 

9

Son Tay – splitting point Hoa Binh – Viet Tri

2

x

3

6

 

10

Duong Kinh – splitting point Dong Hoa – Dinh Vu

4

x

3

12

 

11

Thuy Nguyen – splitting point Hai Phong – Vat Cach

4

x

1

4

 

12

Dong Hoa - Thai Binh

1

x

54

54

For Circuit 2

13

Hai Duong 2 – splitting point Dong Hoa – Pha Lai

2

x

2,5

5

 

14

Hai Duong 2 – Mao Khe TPP

2

x

22

44

 

15

Hai Duong TPP – Pho Noi 500kV

2

x

60

120

Connected to Hai Duong TPP

16

Hai Duong TPP – splitting point Pha Lai – Hai Duong 2

4

x

2

8

Connected to Hai Duong TPP

17

Kim Dong - Thai Binh

2

x

70

140

 

18

Thai BInh - Thai Binh TPP

2

x

25

50

 

19

Connection to Phoi Noi 500kV – Pho Noi – Pha Lai

4

x

5

20

 

20

Pho Noi 500kV – Tien Son (Bac Ninh 2)

2

x

30

60

 

21

Truc Ninh – splitting point Nam Dinh – Ninh Binh

2

x

18

36

 

22

Truc Ninh - Thai Binh TPP

2

x

45

90

 

23

Nho Quan – Phu Ly

2

x

38,5

77

Existing line shall be used

24

Tuan Giao – Son La

2

x

90

180

 

25

Cao Bang – Bac Kan

2

x

78

156

 

26

Cao Bang – Nho Que HPS

2

x

98

196

 

27

Bac Kan – splitting point Thai Nguyen – Tuyen Quang HPS

2

x

20

40

 

28

Lao Cai – Bao Thang

1

x

20

20

 

29

Bao Thang – Bac Ha HPS

1

x

30

30

 

30

Bao Thang – Yen Bai

2

x

125

250

 

31

Than Uyen – Ban Chat

2

x

26

52

 

32

Lang Son – Bac Giang

2

x

95

190

 

33

Phu Tho – splitting point Viet Tri – Yen Bai

2

x

7

14

 

34

Yen Son HPS – splitting point Tuyen Quang HPS – Tuyen Quang

2

x

8

16

 

35

Luu Xa – splitting point Soc Son – Thai Nguyen

2

x

2

4

 

36

Viet Tri – Viet Tri 500kV substation

2

x

2

4

 

37

Connection – Viet Tri 500kV substation

4

x

2

8

 

38

Soc Son – Ba Thien

2

x

30

60

 

39

Quang Chau – splitting point Pha Lai – Soc Son

2

x

3

6

 

40

Establishing connection to Hiep Hoa 500kV substation

8

x

3

24

 

41

Khe Than – splitting point Son Dong – Trang Bach

2

x

2

4

 

42

Yen Hung – splitting point Uong Bi – Trang Bach

2

x

15

30

 

43

Mao Khe TPP – splitting point Pha Lai – Trang Bach

4

x

3

12

 

44

Hai Ha – Cam Pha

2

x

85

170

For circuit 1

45

Huoi Quang – Son La

2

x

20

40

 

46

Huoi Quang – Ban Chat

2

x

22

44

 

47

Nam Chien – Son La

2

x

18

36

 

48

Yen Thuy – splitting pointed Hoa Binh – Nho Quan

2

x

1

2

 

49

Nghi Son – Nghi Son TPP

2

x

15

30

 

50

Nghi Son – Thanh Hoa

2

x

70

140

Under construction

51

Nam Sum 1 TPP – Hua Na HPS

2

x

35

70

 

52

Hua Na HPS – Bim Son

1

x

80

80

Connected to circuit 2 of the line Nam Sum 1 – Hua Na

53

Bim Son – splitting point Ninh Binh – Thanh Hoa

2

x

3

6

 

54

Quynh Luu – splitting point Nghi Son - Vinh

2

x

2

4

 

55

Nam Mo – Ban La

2

x

120

240

Must ensure sufficient transmission for the HPSs in the area

56

Establishing connection to Cong Thanh TPP

4

x

50

200

 

57

Ha Tinh – Thach Khe

2

x

20

40

 

58

Ha Tinh – Vung Ang

2

x

70

140

 

59

Vung Ang – Dong Hoi

2

x

90

180

 

60

Thuong Tin – Kim Dong

2

x

27

54

 

 

Central area

 

 

 

2867

 


tải về 2.28 Mb.

Chia sẻ với bạn bè của bạn:
1   ...   7   8   9   10   11   12   13   14   ...   19




Cơ sở dữ liệu được bảo vệ bởi bản quyền ©hocday.com 2024
được sử dụng cho việc quản lý

    Quê hương