60 QD-TTg 340588

No.

Name of pipeline

Operation commencement period

Expected capacity (billion m3/year)

Length (km)

Diameter (inch)

I

Main offshore gas pipeline system





1

Ham Rong – Thai Binh gas gathering pipeline (2nd stage)

2018 - 2020

0.5

53

12

II

Low-pressure gas pipeline system and CNG station





1

Pipeline system for distribution of low-pressure gases to Tien Hai area (2nd stage)

2018 - 2020

0.25

30

6 - 10

2

Tien Hai CNG distribution system (2nd stage)

2018 - 2025

0.35



+ 2026 – 2035 period:

No.

Name of pipeline

Operation commencement period

Expected capacity (billion m3/year)

Length (km)

Diameter (inch)

I

Main offshore gas pipeline system





1

Pipeline for gathering of gases from other potential gas fields at Block 102/106 & 103/107 to Tien Hai’s shore

2030 - 2035

2

80 - 100

10 - 16

II

Gas gathering pipelines





1

Pipelines for gathering of gases produced from potential gas fields such as Hong Long, Hac Long, Bach Long, Dia Long, etc. at Blocks 102/106&103/107

2030 - 2035

0.2 – 0.5

70 - 80

8 - 10

2

Pipeline for gathering of gases from potential gas fields at Blocks 102/106 & 103/107 linked with Ham Rong, Thai Binh gas gathering pipelines

2032 - 2035

0.2 – 0.5

40 - 50

8 - 10

III

Onshore high-pressure gas pipeline system





1

High-pressure pipeline system for transportation of gases produced by potential gas wells at Blocks/ gas fields in the Red River basin area from LFS Tien Hai to Thai Binh area

2032

1.5 - 2

6

16

2

Pipeline system for transmission of gases from Northern region’s LNG storage unit to Northern region’s power plants

2025 - 2030

2

15 - 20

20

IV

Low-pressure gas distribution pipeline and CNG manufacturing system





1

Pipeline system for distribution of low-pressure gases to Tien Hai area (3rd stage)

2026 - 2035

0.25

30 - 50

6 - 10

2

CNG manufacturing system at Tien Hai (3rd stage)

2026 - 2035

0.25



- Central region:
+ 2016 – 2025 period:

No.

Project

Operation commencement period

Expected capacity (billion m3/year)

Length (km)

Diameter (inch)

I

Main offshore high-pressure gas pipeline system





1

Pipeline for gas transmission from Ca Voi Xanh gas field to Quang Nam province

2023 - 2025

9 - 11

80 - 100

32 - 36

2

Pipeline system for transmission of gases from Bao Vang gas field to Quang Tri province

2023 - 2025

2 - 3

120

16

II

Onshore gas pipeline system





1

High-pressure gas pipeline from GTP at Tam Quang to Quang Nam, Quang Ngai power plant and the petrochemical complex located at Dung Quat Economic Zone

2023 - 2025

8

25

26

2

Pipeline system from gas distribution center (GDC) in Tam Quang to industrial parks (IP) in Quang Nam province

2023 - 2025

0,6 - 0,9

10 - 15

8 - 10

3

Pipeline system from the gas distribution station (GDS) in Dung Quat to Dung Quat industrial park

2023 - 2025

0.7

10 - 15

8 - 10

III

Low-pressure gas distribution pipeline system





1

Low-pressure gas distribution pipeline system

2023 - 2025

0.3



IV

Gas treatment plant





1

Gas treatment plant (GTP) in Quang Nam province

2023 - 2025

9 - 11



V

CNG and petrochemical plant/station





1

CNG/LNG plant in the Central region

2023 - 2025

0.20 – 0.25



+ 2026 – 2035 period:

No.

Project

Operation commencement period

Expected capacity (billion m3/year)

Length (km)

Diameter (inch)

I

Gas gathering pipelines





1

Pipeline system for gathering of gases from gas production wells at Block 105-110 and Block 111-11 linked with Bao Vang – Quang Tri pipeline

After 2033

-

60 - 80

10 - 16

2

Pipeline system for gathering of gases from potential gas production well at Block 115-119 linked with the pipeline of Ca Voi Xanh gas field

After 2033

-

150 - 200

12 - 20

II

Onshore high-pressure gas pipeline





1

High-pressure pipeline from GDC to power plants in Quang Tri province

2033

1.5

10

16

III

Gas treatment plant





1

Gas processing plant (GPP) in Quang Tri province.

2033

2 - 3



- Southeast region:
+ 2016 – 2025 period:

No.

Name of pipeline

Operation commencement period

Expected capacity (billion m3/year)

Length (km)

Diameter (inch)

I

Main offshore high-pressure gas pipeline system





1

Nam Con Son 2 gas pipeline system – 2nd stage – from KP 207 - LFS

2019

7

117

26

2

Nam Con Son 2 gas pipeline system – 2nd stage – from KP 207 - LFS

2019 - 2025

7

50 - 60

26

II

Gas gathering pipelines





1

Gas transmission pipeline for gathering of gases from Su Tu Trang gas field to Nam Con Son 2

2019 - 2020

2 - 4

75 - 125

16 - 20

2

King Ngu – Rang Dong gas field gathering pipeline system

2017

0.35

18

12

3

Increase in compression capacity at Bach Ho

2018 - 2019

0.6 – 1.2

-

-

4

Ca Rong Do – Nam Con Son 1 gas field gathering pipeline

2018 - 2019

2.4

83 - 157

16

5

Pipeline for gathering of gases from Cobia gas field linked to Ca Rong Do – Lan Tay pipeline

2020 - 2025

1

5

16

6

Pipeline for gathering of gases from Ca Kiem Den gas field linked to Ca Rong Do – Lan Tay pipeline

2020 - 2025

1

10 - 15

12 - 14

7

Pipeline for gathering of gases from Ca Kiem Nau gas field linked to Ca Rong Do – Lan Tay pipeline

2020 - 2025

1.5

30 - 35

12 - 16

8

Phong Lan Dai – Lan Tay gas field gathering pipeline

2020 - 2025

1.5

20 - 25

12 - 16

9

Song Ngu – Kinh Ngu Trang gas field gathering pipeline system

2021

-

17

12

10

Lead A – Kinh Ngu Trang gas field gathering pipeline system

2025

-

29

12

11

Pipeline linking the central compression platform at Bach Ho to Nam Con Son 2

2019

7

14

26

12

Sao Vang/Dai Nguyet - Nam Con Son 2 gas transmission pipeline system – 1st stage

2019 - 2021

2 - 3

25 - 50

16 - 26

13

Sao Vang/Dai Nguyet - Nam Con Son 1 gas transmission pipeline system (KP75)

2021 - 2025

2 - 3

35

20 - 26

14

Pipeline for connection between BK platform – Thien Ung and Sao Vang/Dai Nguyet

2019 - 2021

1 - 2

25

16