PROJECT INFORMATION FORM

(Project information form)

  • Project type: Urban technical infrastructure

(Project type: for example: Infrastructure - Urban Railway, Infrastructure - Ports, Housing, Health care...).

  • Project Name: Rạch Tra Sluice gate for tidal control

(Project name)

Location: Củ Chi District, Hóc Môn District

(Location)

  • Area square:

(Total land, water surface to be used)

  • Projected Investment: VND 1,122 billion (US$ 51 million)

(The expected investment capital, denominated in VND and USD)

  • Investment type: ODA, PPP,…

(Form of investment, ODA, PPP, OBT, FDI and other forms proposed by the Investor)

  • Objectives:

(Project objective)

General information: Technical specifications: Drainage width: 2x40 m, bottom elevation: 5m. Decision No. 5754/QĐ-UBND dated 12/11/2012 of the People’s Committee of the city on approving the portfolio of investment projects under BOT and BT form in the city

(General information on the project: Policy to call for investment, planning information, land compensation and clearance, project operation term, investment preferences (if any)…)

  • Pictures: master plan, map, design, illustration … (PC file formats, quality and size enough for printing)

(Image: master plan, map, design, illustration ... (PC format, quality and size enough for printing) 

  • Contact agency: Department of Transportation and Communication

(Contact agency)






PROJECT INFORMATION FORM

(Project information form)

  • Project type: Transport infrastructure

(Project type: for example: Infrastructure - Urban Railway, Infrastructure - Ports, Housing, Health care...).

  • Project Name: Constructing Nguyễn Văn Linh intersection - Phạm Hùng, Bình Chánh

(Project name)

Location: Bình Chánh District

(Location)

  • Area square:

(Total land, water surface to be used)

  • Projected Investment: VND 753 billion (equivalent to USD 34 million)

(The expected investment capital, denominated in VND and USD)

  • Investment type:

(Form of investment, ODA, PPP, OBT, FDI and other forms proposed by the Investor)

  • Objectives: Constructing Nguyễn Văn Linh intersection - Phạm Hùng in order to satisfy traffic needs in the area

(Project objective)

General information:

- HC1 underpass on Nguyễn Văn Linh Street - in the direction from Nguyễn Văn Linh Street - Highway 1A to Tân Thuận Export Processing Zone.

- HC2 underpass on Nguyễn Văn Linh Street - toward Tân Thuận EPZ via National Highway 1A

- Constructing the central roundabout



(General information on the project: Policy to call for investment, planning information, land compensation and clearance, project operation term, investment preferences (if any)…)

  • Pictures: master plan, map, design, illustration … (PC file formats, quality and size enough for printing)

(Image: master plan, map, design, illustration ... (PC format, quality and size enough for printing) 

  • Contact agency: Urban Traffic Control Section No.4

(Contact agency)



THỦ THIÊM NEW URBAN AREA PROJECT




  1. Project type: Tourism

  1. Project title:

The Project of urban resort hotels

  1. Location:

The land lot has the number 7-1 and is in the Functional area no. 7 in Thủ Thiêm new urban area; parcel no. 3, map no. 36 of Bình Khánh Ward. The Project is constructed on a separate land lot where is the current combination of Canals in the East of Thủ Thiêm new urban area, with water traffic routes around the land lot.

  1. Total land area: 6.8 ha

  1. Project objectives:

Constructing high-class hotels for domestic and foreign tourists

  1. The expected investment capital: VND 2,760 billion (equivalent to USD 125 million)

  1. General information on the project:

The investors who are selected to implement the projects will carry out the planning and submit the planning for approval according to regulations. Some planning criteria (under the approved allocating plan at ratio 1/2000)

  1. Form of investment:

Call for domestic and foreign investments to implement the investment project with land use (in form of land use right auction)

  1. Contact address:

Thủ Thiêm New Urban Area Investment - Construction Management Board

Address: No. 177 Lý Chính Thắng, Ward 7, District 3, Hồ Chí Minh City.

Tel: 84.8.35 261 299; Fax: 84.8.35 261 272







  1. Project type: Education - Training

  1. Project title:

Constructing schools up to international standards

  1. Location:

The land lot No. 4-1 is in the Functional area No. 4 in Thủ Thiêm new urban area, District 2, HCMC.

Project is located at the Canal no. 3 in the Northern residential area, at a nice and quiet location, suitable for education of knowledge, physical exercises as well as encouragement of learning spirit and nature love



  1. Total land area: 2 ha

  1. Project objectives:

Constructing vocational basic secondary school

  1. The expected investment capital: VND 200 billion (equivalent to US$ 9 million)

  1. General information on the project:

The investors who are selected to implement the projects will carry out the planning and submit the planning for approval according to regulations. Some planning criteria (under the approved allocating plan at ratio 1/2000)

- Area of land for project development: 20,124 m2

- Area of constructed floor: 10,000 m2

- Floor area ratio (FAR) : 0.50

- Number of floors: 4 floors


  1. Form of investment:

Call for domestic and foreign investments to implement the investment project with land use (in form of land use right auction) the land lot no.

  1. Contact address:

Thủ Thiêm New Urban Area Investment - Construction Management Board

Address: No. 177 Lý Chính Thắng, Ward 7, District 3, Hồ Chí Minh City.

Tel: 84.8.35 261 299; Fax: 84.8.35 261 272







  1. Project type: Education - Training

  1. Project title:

Constructing schools up to international standards

  1. Location:

The land lot No. 3-4 is in the Functional area No. 3 in Thủ Thiêm new urban area, District 2, HCMC.

Project is located right next to the central lake in the Northern residential area, at a nice and quiet location, suitable for education of knowledge, physical exercises as well as encouragement of learning spirit and nature love



  1. Total land area: 1.4 ha

  1. Project objectives:

Constructing basic primary-to-secondary schools

  1. The expected investment capital: VND 100 billion (equivalent to US$ 5 million)

  1. General information on the project:

The investors who are selected to implement the projects will carry out the planning and submit the planning for approval according to regulations. Some planning criteria (under the approved allocating plan at ratio 1/2000)

- Area of land for project development: 13,539 m2

- Area of constructed floor: 10,000 m2

- Floor area ratio (FAR) : 0,74

- Number of floors: 4-6 floors


  1. Form of investment:

Call for domestic and foreign investments to implement the investment project with land use (in form of land use right auction) the land lot no.

  1. Contact address:

Thủ Thiêm New Urban Area Investment - Construction Management Board

Address: No. 177 Lý Chính Thắng, Ward 7, District 3, Hồ Chí Minh City.



Tel: 84.8.35 261 299; Fax: 84.8.35 261 272



NEWLY ADDED PROJECTS




  1. Project type: Education - Training

  1. Project title:

Education project 44.26 ha

  1. Location:

North-Western Urban Area

  1. Total land area: 44.26

  1. Project objectives:

Constructing educational institutions of different levels in the North-Western Urban Area

  1. The expected investment capital: TBD

  1. General information on the project:

Current land status: not yet finished in land compensation and clearance

  1. Form of investment:

PPP, socializations and other forms proposed by the Investor...

  1. Contact address:

North-Western Urban Area Management Board






  1. Project type: Education - Training

  1. Project title:

Education project 85.26 ha

  1. Location:

North-Western Urban Area

  1. Total land area: 85.26 ha

  1. Project objectives:

Constructing educational institutions of different levels in the North-Western Urban Area

  1. The expected investment capital: TBD

  1. General information on the project:

Current land status: not yet finished in land compensation and clearance

  1. Form of investment:

PPP, socializations and other forms proposed by the Investor...

  1. Contact address:

North-Western Urban Area Management Board






  1. Project type: land use

  1. Project title:

Residential - multiple functional trading

  1. Location:

Thủ Thiêm New Urban Area

  1. Total land area: 92,428 m2

  1. Project objectives:

Constructing residential and multiple functional trading area

  1. The expected investment capital: TBD

  1. General information on the project:

Some planning criteria (under the approved allocating plan at ratio 1/2000)

- Area of land for project development: 92,428 m2

- Area of constructed floors: 817,500

- Floor area ratio (FAR) : 9,43

- Number of floors: 10-50 floors


  1. Form of investment:

Call for domestic and foreign investments to implement the investment project with land use (in form of land use right auction) the land lot no.

  1. Contact address:

Thủ Thiêm New Urban Area Investment - Construction Management Board

Address: No. 177 Lý Chính Thắng, Ward 7, District 3, Hồ Chí Minh City.



Tel: 84.8.35 261 299; Fax: 84.8.35 261 272






  1. Project type:

  1. Project title:

Giồng Ông Tố Bridge and intersections at both ends of the Bridge

  1. Location:

District 2

  1. Total land area:

  1. Project objectives:

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment:




  1. Contact address:

District 2






  1. Project type:

  1. Project title:

Road along Sài Gòn River (the section from Hàm Long artisan village project to Phú Mỹ Bridge)

  1. Location:

District 2

  1. Total land area:

  1. Project objectives:

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment:




  1. Contact address:

District 2






  1. Project type:

  1. Project title:

The Parallel Road in the North along Hồ Chí Minh - Long Thành - Dầu Giây Expressway

  1. Location:

District 2

  1. Total land area:

  1. Project objectives:

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment:




  1. Contact address:

District 2






  1. Project type:

  1. Project title:

Đỗ Xuân Hợp Road, building line: 30:40m (the road section from Xuyên Tâm Road to Nam Lý Bridge)

  1. Location:

District 2

  1. Total land area:

  1. Project objectives:

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment:




  1. Contact address:

District 2






  1. Project type:

  1. Project title:

Shallow port area

  1. Location:

PO Lot, bordered by Ông Nhiều River, District 9

  1. Total land area:

6 ha

The length of the ports is 1.500 m (expected 05 ports).



  1. Project objectives:

Size of the works:

+ Warehouse, container yards

+ Barge dock area

+ Operational office area

+ Transport infrastructure


  1. Expected total investment:

  1. General information on the project:

Size of the port: Type II inland marine port (Circular No. 61/2014/TT-BGTVT dated 07/11/2014 of the Ministry of Transport regulating the classification criteria of inland marine ports and publication of the inland marine harbors

The projected maximum capacity: 800 containers/day and night (mainly for investors in High-tech Zone).

Planning: Official Letter No. 586/UBND-DT dated 09/02/2017 of the City's People's Committee to the Ministry of Transport about the plan for development of shallow port system by 2020, oriented to the year 2030


  1. Form of investment:

- Calling for investment from domestic and international investors.

- The Saigon Hi-tech Park Management Board shall guide investors to file investment registration procedures.

- In case there are many investors interested in the project, the Saigon Hi-tech Park Management Board will hold a bidding to select investors.


  1. Requirements for investors:

- Having financial capacity to implement the project

- Having experience in implementing similar projects

- Implementing the project well on schedule


  1. Contact address:

Saigon Hi-tech Park Management Board

Address: Lot T2-3, D1 Street, Saigon Hi-Tech Park, Tân Phú Ward, District 9, Hồ Chí Minh City

Tel: (+84) 3736 0293

Fax: (+848) 3736 0292

Email: xtdt.shtp@tphcm.gov.vn

Website: www.shtp.hochiminhcity.gov.vn








  1. Project type:

  1. Project title:

Duong Cong Khi Industrial Complex

  1. Location:

Xuân Thới Thượng Commune - Hóc Môn District

  1. Total land area: 46.41 ha

  1. The objective of the project: Investment in constructing infrastructure (technical, transportation...)

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment: PPP




  1. Contact address:

Department of Industry and Trade of HCMC

Address: 163 Hai Bà Trưng, W6, D3, HCMC








  1. Project type:

  1. Project title:

Hưng Long University Area

  1. Location:

Hưng Long Commune, Bình Chánh District

  1. Total land area: 511.0 ha

  1. Project objective: Removing universities and colleges currently in the city; being the area of universities, colleges and research institutes

  1. The expected investment capital: TBD

  1. General information of the project: The land has not yet been compensated for site clearance; The City's People's Committee has approved the task of planning: scale: 1/2000 in the decision No. 1395/QD-UBND dated 25/03/2016

  1. Form of investment: TBD

  1. Contact address:

Management Authority of Southern Area Development





  1. Project type:

  1. Project title:

The downtown and residential area West of the City

  1. Location:

Tân Kiên Commune, Bình Chánh District

  1. Total land area: 239.9 ha

  1. Project objective: the City-level center area to the West (Service Trading Finance and Office Center, tourist culture service center; exhibition, research, agricultural development assistance center; Sports Center; mixed service center, ...); existing residential and new residential area; Bình Chánh development dynamic axis

  1. The expected investment capital: TBD

  1. Project information: There is no resource for implementing the planning; newly built residential areas. HTKT & HTXH has not yet been compensated with regard to site clearance; The People's Committee has approved the zoning planning: scale: 1/2000 in the Decision No. 4956/QD-UBND dated 11/09/2013

  1. Form of investment: TBD

  1. Contact address:

Bình Chánh District's People's Committee





  1. Project type:

  1. Project title:

Cần Giờ Resort and Tourist Site - Cần Giờ Prograding Urban Area

  1. Location:

Cần Giờ District

  1. Total land area: 73.3 Km2

  1. Project objective: Developing the economy of Cần Giờ District and Hồ Chí Minh City towards a breakthrough in tourism, entertainment and service economy.

  1. The expected investment capital: Unknown

  1. General information of the project: The contest for the best planning is under way, and the zoning planning: scale: 1/2000 is under establishment for the prograding zone of 2780ha

  1. Form of investment: TBD

  1. Contact address:

People's Committee of Cần Giờ District





  1. Project type:

  1. Project title:

Saigon Safari Park

  1. Location:

Củ Chi District

  1. Total land area: 456.34 ha

  1. Project objective: Building an urban park

  1. The expected investment capital: Unknown

  1. General information of the project: Clean land, and the construction site zoning planning, scale: 1/2000 has been approved

  1. Form of investment: unknown

  1. Contact address:

DPI





  1. Project type:

  1. Project title:

Expanding and upgrading Nguyễn Thị Rành Road

  1. Location:

The section through Saigon Safari Park

  1. Total land area:

  1. Project objectives: Investing in urban technical infrastructure for economic development in Củ Chi District

  1. The expected investment capital: Unknown

  1. General information of the project: Clean land, and the construction site zoning planning, scale: 1/2000 has been approved

Form of investment: unknown

  1. Contact address:

DPI





  1. Project type:

  1. Project title:

Expanding and upgrading Tam Tân Road

  1. Location:

The section of the North West Urban Area of the City

  1. Total land area:

  1. Project objective: Investing in technical infrastructure for development of the North West Urban Area of the City

  1. The expected investment capital: Unknown

  1. General information of the project: The land has not yet been compensated; the site zoning planning, scale: 1/2000 has been approved

  1. Form of investment: unknown

  1. Contact address:

North West Urban Area Management Board





  1. Project type:

  1. Project title:

Compensation for site clearance and resettlement for separation greenery in Đa Phước waste treatment complex and cemetery

  1. Location:

Đa Phước Waste treatment complex and cemetery

  1. Total land area: 268ha

  1. Project objectives:

  1. The expected investment capital: VND1,069 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Department of Finance; Department of Planning and investment; Bình Chánh People's Committee; Bình Chánh District Committee for Site Clearance Compensation; the City's Compensation Appraisal Council

  1. Notes (schedule, status): City People's Committee, Document No. 4644/UBND -TMT dated 10/08/2015 approving the policy to continue implementing the project. The People's Council of the City has approved the policy in the Resolution No. 07/NQ-HDND dated 21/04/2016. The project has been allocated VND 2 billion for investment preparation





  1. Project type:

  1. Project title:

The project of planting separation greenery in Đa Phước solid waste treatment complex and cemetery

  1. Location:

Đa Phước Waste treatment complex and cemetery

  1. Total land area: 268ha

  1. Project objectives:

  1. The expected investment capital: VND 90 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Department of Finance; Department of Planning and Investment; Bình Chánh People's Committee; Department of Agriculture and Rural Development.

  1. Notes (Schedule, status): The People's Council of the City has approved the policy in the Resolution No. 07/NQ-HDND dated 21/04/2016. The project has been allocated VND 100 million for investment preparation





  1. Project type:

  1. Project title:

The project of site clearance compensation in phase 2 for separation greenery in Northwest City solid waste treatment complex, Củ Chi District

  1. Location:

Northwest City solid waste treatment complex, Củ Chi District

  1. Total land area: 197 ha

  1. Project objectives:

  1. The expected investment capital: VND 526 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Department of Finance; Department of Planning and investment; Củ Chi People's Committee; Củ Chi District Committee for Site Clearance Compensation; the City's Compensation Appraisal Council

  1. Notes (schedule, status): The project has been approved by the City People's Committee in terms of the policy to continue implementation in the Document No. 4643/UBND -DTMT dated 10/08/2015. The People's Council of the City has approved the policy in the Resolution No. 07/NQ-HDND dated 21/04/2016. The project has been allocated VND 2 billion for investment preparation





  1. Project type:

  1. Project title:

The project of planting separation greenery in the Northwest City solid waste treatment complex, phase 2

  1. Location:

Northwest City solid waste treatment complex

  1. Total land area: 197ha

  1. Project objectives:

  1. The expected investment capital: VND 70 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (schedule, status): The City People's Committee has issued Decision No. 6821/UBND-DTMT dated 29/12/2016 approving the investment policy. The project has been allocated VND 200 million for investment preparation





  1. Project type:

  1. Project title:

The project of site clearance compensation in phase 3 for separation greenery in Northwest City solid waste treatment complex, Củ Chi District

  1. Location:

Northwest City solid waste treatment complex, Củ Chi District

  1. Total land area: 67ha

  1. Project objectives:

  1. The expected investment capital: VND 350 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (Schedule, status): The People's Council of the City has approved the policy in the Resolution No. 07/NQ-HDND dated 21/04/2016. The project has been allocated VND 300 million for investment preparation





  1. Project type:

  1. Project title:

The project of planting separation greenery in the Northwest City solid waste treatment complex, phase 3

  1. Location:

Northwest City solid waste treatment complex

  1. Total land area: 67ha

  1. Project objectives:

  1. The expected investment capital: VND 20 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (schedule, status): The City People's Committee has issued Decision No. 6821/UBND-DTMT dated 29/12/2016 approving the investment policy. The project has been allocated VND 100 million for investment preparation






  1. Project type:

  1. Project title:

Calling for investment in public trash bins, public toilets on land, on rivers to meet the need of preserving the environment

  1. Location:

  1. Total land area:

  1. Project objectives:

  1. The expected investment capital: VND 600 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

The project of investment in synchronous collection and transportation equipment. Transportation of domestic solid waste in the city

  1. Location:

  1. Total land area:

  1. Project objectives:

  1. The expected investment capital: VND 2,000 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

The project of investing in construction of automatic air observation stations, automatic surface water observation stations and automatic groundwater observation stations to cover the observation network throughout the city.

  1. Location:

  1. Total land area:

  1. Project objectives:

  1. The expected investment capital: VND 300 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Carrying out the activities of collecting and processing hyacinth to clear the flow on Saigon River, Đồng Nai River, Vàm Cỏ Đông River and the canals between Hồ Chí Minh City and other neighboring provinces such as Bình Dương, Đồng Nai, Long An and Tây Ninh

  1. Location:

Saigon River, Đồng Nai River, Vàm Cỏ Đông River and the canals between Hồ Chí Minh City and other neighboring provinces such as Bình Dương, Đồng Nai, Long An and Tây Ninh

  1. Total land area:

  1. Project objectives:

  1. The expected investment capital: VND 110 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

The project of recycling industrial waste and treating hazardous waste in municipal waste treatment complexes

  1. Location:

The City Waste Treatment Complex

  1. Total land area:

  1. Project objectives:

  1. The expected investment capital: VND 1,470 billion

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Departments; District People's Committee; relevant units

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Resettlement of the cluster of 08 apartment buildings in Thanh Đa Residential Apartment Area, Ward 27

  1. Location:

Cluster of 08 apartment buildings in Thanh Đa Residential Apartment Area, Ward 27

  1. Total land area: 73,211m2

  1. Project objectives:

  1. Expected total investment:

  1. General information of the project: Current population: 4,748 (1,427 units); Function: high-rise apartment combined with trade service complex; floor area ratio: 8; Population size: 7,948; relocated population 4,748; Population increase / decrease: 3,200; number of floors: 30, construction density (%): 40

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Resettling the Cluster of 15 apartment buildings in Thanh Đa Residential Apartment Area, Ward 27

  1. Location:

Cluster of 15 apartment buildings, Thanh Đa Residential Apartment Area, Ward 27

  1. Total land area: 149,350m2

  1. Project objectives:

  1. Expected total investment:

  1. General information of the project: Current population: 10,820 (2,705 units); Function: high-rise apartment combined with trade service complex; floor area ratio: 10; Population size: 17,220; relocated population 10,820; Population increase / decrease: 6,400; number of floors: 30, construction density (%): 40

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Resettlement of the Bank Apartment Building No. 18 Phan Chu Trinh, Ward 2

  1. Location:

The Bank Apartment Building No. 18 Phan Chu Trinh, Ward 2

  1. Total land area: 1,960m2

  1. Project objectives:

  1. Expected total investment:

  1. General information of the project: Land area suitable for planning (m2): 1,959.20; current population: 128; Planning building line: 25; Function: high-rise apartment building; index m2 / person: 4; floor area ratio: 10; Population size: 490; relocated population 236; Population increase / decrease: 254; number of floors 22, construction density (%): 45. Floor area ratio (+1.25) near Metro station <400m, 30% reserved for green park; (-1) road <26m

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status): Resettlement for 15 households at 199/43A Lê Quang Định, Ward 7, and 12 households at the Apartment Building, 66 Trần Văn Kỳ, Ward 14






  1. Project type:

  1. Project title:

Resettlement of the apartment building at No. 2 Lê Quang Định, Ward 14

  1. Location:

Apartment building at No. 2 Lê Quang Định, Ward 14

  1. Total area of ​​land: 1640.8 m2 (extension of boundary) and 553.1 m2 (existing)

  1. Project objectives:

  1. Expected total investment:

  1. General information of the project: Land area suitable for planning (m2): 553.1; current population: 108; planning building line: 25-30; Function: trade-service combined with residential apartment building.

  • For the area of ​​the boundary expansion: m2 / person norm: 3; Floor area ratio: 10.5; Population size: 480; Relocated population: 204; Population increase / decrease: 276; number of floors: 18, Construction density (%): 60. Floor area ratio (+3) near Metro station<400m, site clearance;

  • For the area of ​​the existing land plot: m2 / person norm: 3; Floor area ratio: 10.5; Population size: 184; Relocated population: 108; Population increase / decrease: 76; number of floors: 18, Construction density (%): 60.

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status): Number of floors, construction density follow Bà Chiểu Trade Center. On-site resettlement of 12 boundary expansion households and 12 households at 189/16 Hoàng Hoa Thám, Ward 6






  1. Project type:

  1. Project title:

Resettlement of the Apartment building in alley 23 Trần Văn Kỳ, Ward 14

  1. Location:

Apartment building in alley 23 Trần Văn Kỳ, Ward 14

  1. Total land area: 1,372.8 m2 (boundary expansion) and 1,119 m2 (existing)

  1. Project objectives:

  1. Expected total investment:

  1. General information of the project: Land area suitable for planning (m2): 1,119; current population: 160; Planning building line: 5.

  • For the area of ​​the boundary expansion: Function: high-rise apartment building; m2 / person norm: 3; Floor area ratio: 8.4; Population size: 446; Relocated population: 212; Population increase / decrease: 234; number of floors: 14, Construction density (%): 60. Floor area ratio (+2) near Metro station <400m, large plot, site clearance compensation completed; (-3) not adjoining road> 16m.

  • For the area of ​​the existing land plot: The land plot has only 01 current road less than 7.0 m, difficult to connect infrastructure and ensure fire protection; the current status should be maintained or the functions of the works should be adjusted

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status): Resettlement of 13 additional households for boundary expansion






  1. Project type:

  1. Project title:

Resettlement of railway apartment building, 28 Phạm Viết Chánh, Ward 19

  1. Location:

Railway Building, 28 Phạm Viết Chánh, Ward 19

  1. Total land area: 792m2

  1. Project objectives:

  1. Expected total investment:

  1. General information of the project: Land area suitable for planning (m2): 792; current population: 60; Planning building line: 6; Function: low-rise apartment building; m2 / person norm: 3.5; floor area ratio: 4.2; Population size: 226; relocated population: 116; Population increase / decrease: 110; number of floors: 7, construction density (%): 60.

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status): Resettlement for 08 households at No. 11/A2 XVNT, Ward 17 and 06 households at No. 02 Nguyễn Hữu Thoại, Ward 19






  1. Project type:

  1. Project title:

Resettlement of the Apartment Building 4B Xô Viết Nghệ Tĩnh, Ward 19 and Công Trường Hòa Bình Apartment Building. Ward 19

  1. Location:

Apartment Building 4B Xô Viết Nghệ Tĩnh, Ward 19 and Công Trường Hòa Bình Apartment Building. Ward 19

  1. Total area of ​​land: 6,549.3 m2 (extension of boundary) and 4,752.3 m2 (existing)

  1. Project objectives:

  1. Expected total investment:

  1. General information of the project: Land area suitable for planning (m2): 1,140; current population: 288; Planning building line: 30; Function: high-rise apartment building.

  • For the area of ​​the boundary expansion: m2 / person norm: 3; Floor area ratio: 10.5; Population size: 2,183; Relocated population: 1,024; Population increase / decrease: 1,057; number of floors: 25, Construction density (%): 45. Floor area ratio (+2) near Metro station<400m, site clearance compensation done;

  • For the area of ​​the existing land plot: m2 / person norm: 3; Floor area ratio: 10.5; Population size: 1,584; Relocated population: 876; Population increase / decrease: 708; number of floors: 25, Construction density (%): 45. Floor area ratio (+2) near Metro station<400m, site clearance compensation done;

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status): resettlement of additional 37 households for boundary expansion, 16 households at 33 Nguyễn Hữu Thoại and 23 households at 06 Phạm Viết Chánh and resettlement of 16 households at 33 Nguyễn Hữu Thoại and 23 households at 06 Phạm Viết Chánh






  1. Project type:

  1. Project title:

Xuyên Tâm canal project

  1. Location:

Xuyên Tâm Canal

  1. Total land area:

  1. Project objectives:

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment:

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status): Decision No. 1025 / QD-UBND dated 10/03/2016 of the City's People's Committee on approval of investment project proposal.






  1. Project type:

  1. Project title:

Renovation of the houses on the edge of Văn Tánh canal

  1. Location:

Văn Thánh Canal

  1. Total land area:

  1. Project objectives:

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Bình Thạnh District People's Committee

  1. Notes (schedule, status): According to Official Letter No. 7253/UBND-QLDA dated 26/11/2015 on proposal of renovating the houses on the edge of Văn Thánh Canal. Bình Thạnh District in the form of PPP






  1. Project type:

  1. Project title:

Building new headquarters of the District Party Committee, People's Committee of Hóc Môn District

  1. Location:

Hóc Môn town

  1. Total land area: 5,020.4 m2 (excluding the building line)

  1. Project objective: Building new headquarter offices of District Party Committee, People's Committee of Hóc Môn District to meet the working needs of staffs as well as citizens who come to work in the headquarter offices of District Party Committee, People's Committee, also contributing to socio-economic development in Hóc Môn District

  1. The expected investment capital: VND 138,653 billion

  1. General information on the project: Total area of ​​constructed floors: 11,600 m2; 07 floors.

  1. Form of investment: PPP

  1. Contact address:

Hóc Môn District Construction Investment Management Board.

Address: No. 09, Nguyễn Thị Sóc Street, Bà Điểm Commune, Hóc Môn District. Tel: 028 38.832.908



  1. Notes (schedule, status): Applying for investment policy






  1. Project type:

  1. Project title:

Expanding Highway 13

  1. Location:

Hiệp Bình Chánh Ward và Hiệp Bình Phước Ward

  1. Total land area:

  1. Project objective: Completing the traffic infrastructure as planned for socio-economic development

  1. The expected investment capital: VND 6500 billion

  1. General information on the project: Expanding Highway 13 as planned

  1. Form of investment: BT

  1. Contact address:

Department of Transportation and Communication of Hồ Chí Minh City

Address: 63 Lý Tự Trọng Street, Bến Nghé Ward, District 1.



  1. Note (schedule, status): Official Letter No. 591/TB-VP dated 17/08/2017 of the Office of the District People's Committee announcing the conclusions of the Standing People's Committee of the District in the 33rd week meeting of the District People's Committee on 14/08 / 2017






  1. Project type:

  1. Project title:

Upgrading Hóc Môn - Bắc Bình Chánh irrigation system

  1. Location:

Hóc Môn District, Bình Chánh District and Tân Bình District - Hồ Chí Minh City

  1. Total land area:

  1. Project objectives: Upgrading the irrigation system in line with the new planning and new situation in order to serve multiple sectors and multiple purposes for the development of urban agriculture, industry and people's life, building new rural areas and meeting the conditions of climate change and sea level rise.

  1. The expected investment capital: VND 485 billion (equivalent to US$ 22.045 million

  1. General information on the project: Dredging main canal route with the total length of L = 70.18 km. - Building new and adding drains at the beginning and end of the canal. - Upgrading 05 pump stations and building 01 new pump station. - Upgrading and replacing valve gate CT3 valve into stainless steel (63 doors).

  1. Form of investment: Foreign direct investment

  1. Contact address:

Irrigation Service Operation Management Company Limited

No. 21, Highway 22, Pump Station Village, Tân Phú Trung Commune, Củ Chi District, Hồ Chí Minh City



  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Investment in the City's Fisheries Center in Cần Giờ District

  1. Location:

Bình Khánh Commune, Cần Giờ District, Hồ Chí Minh City

  1. Total land area: 100ha

  1. Project objective: Establishing centers for trade and logistics for fisheries with advanced technology from other countries in the region, ensuring the aims of implementing Vietnam’s marine strategies

  1. The expected investment capital: VND 1,200 billion (equivalent to US$ 55 million)

  1. General information on the project: Constructing a fishing port and market with the area of ​​20ha along Soài Rạp River. - Constructing infrastructure for aqua-product processing factories, and logistic service facilities for fishing industry with a size of 80ha

  1. Form of investment: PPP; socialization

  1. Contact address:

Management Board of the City's Fisheries Center directly under the Department of Agriculture and Rural Development

Level 4, 176 Hai Bà Trưng Street, Đakao Ward, District 1



  1. Notes (schedule, status): Decision No. 5754/QD-UBND dated 12/11/2012 of the People's Committee of Hồ Chí Minh City approving the list of BOT and BT projects in the city






  1. Project type:

  1. Project title:

Sport area

  1. Location:

No. 2374, National Road 1, Trung Mỹ Tây Ward, District 12.

  1. Total land area: 9,807m2. Number of floors: 2 floors

  1. Project objective: Serving the improvement of health and spiritual life of officials and employees of the Center and people in the vicinity.

  1. The expected investment capital: VND 30 billion (equivalent to US$ 1.4 million)

  1. General information on the project: The project includes 01 soccer field for 11 players, 300 seat stand, one 600m2 multi-purpose sports hall, one tennis court and ancillary facilities.

  1. Form of investment: BOT

  1. Contact address:

Center for Biotechnology

  1. Notes (schedule, status): Currently the product proposal documents have been completed and submitted to the City for approval of investment policy in the form of PPP






  1. Project type:

  1. Project title:

Head office: Department of Agriculture and Rural Development

  1. Location:

No. 176 Hai Bà Trưng Street and 186 Nguyễn Văn Thụ Street, District 1

  1. Total land area: 2533m2

  1. Project objective: Gathering the units under the Department of Agriculture and Rural Development to new office building. - The total number of officials, civil servants and employees is about 570 people.

  1. The expected investment capital: VND 211 billion (equivalent to US$ 10 million)

  1. General information on the project: Construction area: 1,420m2. - 01 basement for parking: 1,420m2. - Total floor area (excluding roof technical floor): 9,940 m2 (07 floors) + 1,420 m2 basement = 11,360 m2

  1. Form of investment: PPP; socialization

  1. Contact address:

Department of Agriculture and Rural Development

No. 176 Hai Bà Trưng Street, Đakao Ward, District 1, Hồ Chí Minh City



  1. Notes (schedule, status): Pending the policy for selection of project proposing units






  1. Project type:

  1. Project title:

Investing in technical infrastructure of Rạch Chiếc National Sport Complex

  1. Location:

An Phú Ward, District 2

  1. Total land area: 180,731ha

  1. Project objectives:

  1. The expected investment capital: VND 1,500 billion

  1. General information on the project: Constructing technical infrastructure to ensure the synchronism of architectural space, urban space and underground space ... to serve as the basis for construction of sports and physical training facilities to organize events, regional and international sporting festivals

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group A project






  1. Project type:

  1. Project title:

50,000 seat stadium

  1. Location:

An Phú Ward, District 2

  1. Total land area: 10ha

  1. Project objective: Building a new stadium of 50,000 seats with integrated running track to serve the official sport events of the world, continent.

  1. The expected investment capital: VND 2,844 billion

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group A project






  1. Project type:

  1. Project title:

Indoor athletic arena with 10,000 seats

  1. Location:

An Phú Ward, District 2

  1. Total land area: 0.4ha

  1. Project objective: Building a 10,000-seat stadium to serve the needs of athletics training, competition and development

  1. The expected investment capital: VND 601 billion

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group B project






  1. Project type:

  1. Project title:

Integrated gymnasium and arena

  1. Location:

An Phú Ward, District 2

  1. Total land area: 0.32 ha

  1. Project objective: Building an integrated sport and physical training ground comprising of a main stadium (10,000 seats) and two start-up and auxiliary stadiums (each with 1,000 seats)

  1. The expected investment capital: VND 2,185 billion

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group A project






  1. Project type:

  1. Project title:

Pan shaped cycle track course

  1. Location:

An Phú Ward, District 2

  1. Total land area: 3.6ha

  1. Project objective: Building a pan-shaped cycle track course incorporating international standards-based stadiums to integrate motorbike race tracks for competition and serving the entertainment needs of the people.

  1. The expected investment capital: VND1,991 billion

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group A project






  1. Project type:

  1. Project title:

Swimming Pool + Springboard pool

  1. Location:

An Phú Ward, District 2

  1. Total land area: 0.2 ha

  1. Project objective: Building swimming pool, springboard pool for water sports training, competition and development.

  1. The expected investment capital: VND 1,365 billion

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group A project






  1. Project type:

  1. Project title:

Shooting and archery field complex

  1. Location:

An Phú Ward, District 2

  1. Total land area: 0.5 ha

  1. Project objective: Building a shooting and archery field complex to serve the needs of shooting and archery training, competition and development.

  1. The expected investment capital: VND 67 billion

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group B project






  1. Project type:

  1. Project title:

06 outdoor football fields

  1. Location:

An Phú Ward, District 2

  1. Total land area: 10ha

  1. Project objective: Investing in construction of 06 European standard football fields and cooperating with famous clubs in the world in training to supplement young football resources and contribute to taking the level of football of Hồ Chí Minh City to new heights.

  1. The expected investment capital: VND 969.9 billion

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status): Group A project






  1. Project type:

  1. Project title:

Water sports complex

  1. Location:

215A Lý Thường Kiệt Street, District 11

  1. Total land area: 3ha

  1. Project objective: Building water sports complex to serve water sports training, competition and development.

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Martial Arts Center

  1. Location:

4 Lê Đại Hành, District 11

  1. Total area: 1.6ha

  1. Project objective: Building a martial arts training area to meet the requirements of forming a modern and well-equipped Martial Arts Center, to act as a focal point for martial arts activities of the Southern region and a place for exchanging and learning martial arts with international martial arts organizations

  1. Expected total investment:

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Culture and Sports

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Renovating and expanding Tôn Thất Thuyết road and Green Park along Tẻ Canal

  1. Location:

District 1

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 738

  1. General information on the project: the road: length: 3,300m, width: 15m
    Embankment section: section of canal through ward 1, 3 (from dry dock alley with Khánh Hội road) is 945m long; The canal section through the wards 4,15,16,18 is 1,450m long; Green Park along Tẻ Canal

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of a road connecting Trần Quốc Hoàn - Cộng Hòa

  1. Location:

Tân Bình District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 547

  1. General information on the project: Length: 4,390m, width: from 20 to 28m

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of Nguyễn Khoái road, District 4 and District 7

  1. Location:

District 4, District 7

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 877

  1. General information on the project: Length: 1.300m, width: 35m

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Upgrading and expanding Dương Quảng Hàm street (the section from Bình Thạnh District to the Culture Park)

  1. Location:

Gò Vấp District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 667

  1. General information on the project: Length: 2,400m, width: 40m

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Upgrading and expanding Nguyễn Ánh Thủ street (from Tô Ký to Lê Văn Khương)

  1. Location:

District 12

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 3,163

  1. General information on the project: Length: 4.7 km, width: 40m

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Upgrading and expanding the district road 80B (from Nguyễn Ảnh Thủ to Lê Văn Khương)

  1. Location:

District 12, Hóc Môn District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 463

  1. General information on the project: 4.3 km long, 20m wide

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of sidewalks, drainage system on Trans-Asia Road (section from An Sương to the beginning of Tây Ninh province)

  1. Location:

Dist. 12, Hóc Môn Province, Củ Chi

  1. Total land area:

  1. Project objective: Strengthening the transport capacity to serve the urbanization process

  1. The expected investment capital: 1,000

  1. General information on the project: 30km long, 40-42m wide

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of inter-ward road of Thới An Ward - Thanh Xuân Ward (route 2)

  1. Location:

District 12

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 1,760

  1. General information on the project: 4,507m long, 30m wide

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Expanding and upgrading Lê Đức Thọ street (from Lê Văn Thọ street to Nguyễn Oanh street)

  1. Location:

Gò Vấp District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 1,048

  1. General information on the project: 3.5km long, 25m wide

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of a steel overpass at the intersection of four communes

  1. Location:

Tân Bình District, Tân Phú District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 934

  1. General information on the project: Thoại Ngọc Hầu - Hương Lộ direction, 280m long, 9m wide in the first phase, in the second phase the same as around

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of steel overpass at Nguyễn Tri Phương - Ngô Gia Tự six-way intersection

  1. Location:

District 10

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 514

  1. General information on the project: Ngô Gia Tự street direction. Bridge length: 190.7m; width 1.9m in phase 1, and a similar bridge nearby in phase 2

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Renovation and expansion of Linh Xuân overpass

  1. Location:

Thủ Đức District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 400

  1. General information on the project: Tunnel from Kha Vạn Cân to Highway 1K, 6 lanes; renovation of the circle R = 22m, branches

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of the intersection for the route from Bà Chiêm Bridge to Hiệp Phước Industrial Park - Bến Lức Long Thành Expressway

  1. Location:

Nhà Bè District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 1,800

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Construction of Sác Forest Road - Bến Lức Long Thành Expressway

  1. Location:

Nhà Bè District

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 2,000

  1. General information on the project:

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Renovation and expansion of Huỳnh Tấn Phát - Lưu Trọng Lư intersection

  1. Location:

District 7

  1. Total land area:

  1. Project objective: Addressing the congestion and traffic accidents in the area

  1. The expected investment capital: 450

  1. General Information on the project: Construction of 380m tunnel with 2 traffic lanes on Huỳnh Tấn Phát Street from Nhà Bè, Cần Giờ and the City Center. The beginning is 20 m prior to the center of Huỳnh Tấn Phát - Lưu Trọng Lư Intersection, and the end is 30 m from the center of Huỳnh Tấn Phát - Street 7 Intersection, with the length of guiding path on each side being 160m

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Controlling erosion in Thanh Đa peninsula (section 3) (Bình Quới, Cây Bàng, Rạch Chùa)

  1. Location:

Bình Thạnh District

  1. Total land area:

  1. Project objective: Controlling river bank, canal bank erosion

  1. The expected investment capital: 999

  1. General Information on the project: 5.37km long

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type:

  1. Project title:

Controlling erosion of Tôm Canal (Phú Xuân Branch) from the head of Phú Xuân Rivulet Mouth to downstream for 1000m

  1. Location:

Nhà Bè District

  1. Total land area:

  1. Project objective: Controlling river bank, canal bank erosion

  1. The expected investment capital: 800

  1. General Information on the project: 300m long

  1. Form of investment: PPP

  1. Contact address:

Department of Transportation and Communication

  1. Notes (schedule, status):






  1. Project type: Entertainment - Public service

  1. Project name: Amusement and Public Service area

(Zone I - Ancient Zone, History - Ethnic Culture Park)

  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 6.5 ha

  1. Project objective: The project is arranged in the main axis of Hanoi Highway and North Ring Road to create the urban appearance for the road and meet the entertainment and public service demand of the residents in the area and the surrounding area.

  1. The expected investment capital: VND 380 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 215/QD-UBND dated 01/17/2017 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the detailed construction planning, scale: 1/500 for the Ancient Zone (Zone I) of the History - Ethnic Culture Park in District 9, Hồ Chí Minh City

+ Construction density: 10-20%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 01-02 floors



  • Construction items: Shopping, entertainment, restaurants, bars, clubs, sports boating, fishing, motels, gas stations, technical stations ....

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Physical training and sports

  1. Project name: Outdoor physical training and sports zone

(Zone IV - Living Activity Area of the History - Ethnic Culture Park)

  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 3.71 ha

  1. Project objective: The project is located next to the South Ring Road in order to diversify the sports, arts and cultural activities to enrich the cultural - historical sector of the Park, creating a sport zone with various types of sports, where comers can perform, compete, participate in healthy sports and entertainment activities, enjoy public cultural performances for residents in District 9 and attracts people to have fun in the Park

  1. The expected investment capital: VND 100 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 15%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 03 floors



  • Construction items: Outdoor Sports and Gym Zone, arena, tennis courts, beverage service and catering sector, technical area




  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Culture - History

Project name: Trường Sơn Forest Representation Park

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 20.19 ha

  1. Project objective: The project is located in the hills south of the Park, where to plant and reconstruct part of Trường Sơn Forest, typical roads, bases and places associated with the history on Hồ Chí Minh trail during the anti-American period to educate about the nation's history for visitors, ....

  1. The expected investment capital: VND 120 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 10%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 02 floors



  • Construction item: Center area, Trường Sơn Forest Representation Zone, reconstruction of landmarks associated with the history on Hồ Chí Minh Trail, outdoor service and camping area, administrative areas and technical service zone, ...




  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Culture - History

Project name: Vietnam Ethnic Culture Village Zone

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. The total area of ​​the land: 42.0 ha

  1. Project objective: The project is located in the hills south of the Park, is one of the important areas in Zone IV of the History - Ethnic Culture Park. The aim is to reproduce, preserve, promote and exploit the cultural heritages of the community of 54 ethnic groups in Vietnam, to introduce to people throughout the country and the world, to meet the needs of healthy entertainment through arts, cultural and culinary activities typical of the ethnic peoples. In this area, the planning shows traditional living space, recreates the community living space, labor and production space, festive culture space, natural environment and landscape. It also recreates the image of traditional houses, public and religious works typical of each ethnic group.

  1. The expected investment capital: VND 50 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 15%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 03 floors



  • Construction item: The Square and Center of the Park for general introduction, the Area to recreate ethnic groups by region (including housing, production areas, festive activity area, traditional production area), food and service area, governance and technical areas, internal roads and grounds, ...




  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Culture - History

Project name: Cinema Park

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 23.28 ha

  1. Project objective: The project is located in the Southwest of the Park, bordering the South Ring Road and Hàng Tre Road in order to create a novelty theme park for the City people, and also create conditions for Vietnam's cinema to develop and approach the public more vividly. The Cinema Park has the function of introducing Vietnam's cinema and organizing activities in the fields of cinema, cinema techniques, providing services for the film crews. This is also where to organize exchanges among actors and the public, hold fun and entertainment activities, ... and cinema activities.

  1. The expected investment capital: VND 500 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 20%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 05 floors



  • Construction item: The Center zone includes the traditional houses, exhibition houses, theaters, ...; internal scene studio, montage technique area; External scene studio area, landscape forest; real and miniature modeling area; amusement area, children's area, swimming pools, performances and services; auxiliary works area (administrative area, management house, warehouse, engineering works); Traffic and parking area.

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Culture - History

Project name: Adventure Park and Peace Square

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 8.08 ha

  1. Project objective: The project is located in the Southwest of the Park adjoining Đồng Nai river and the Village Road No. 33 (in the future it will be the Ring Road 3), forming 01 park with thrilling games for teenagers, linking space with mineral spring resort, forming a major tourist complex complete with various types of diverse entertainment. Especially in this area it is expected to arrange a Peace Square; on the historical significance, this is the result of a process of arduous struggle over the periods from the time of founding the nation (Ancient Zone) to the times against foreign invaders for national freedom and independence (Middle Age and Near modern Zones). In terms of function: this is the area for fun of the people in the region, where to organize outdoor festivals, fireworks, kite flying, cultural and art activities... and where to welcome visitors to the History - Ethnic Culture Park by boats on Đồng Nai River. In terms of landscape, the layout creates open space toward Đồng Nai River.

  1. The expected investment capital: VND 430 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 15%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 05 floors



  • Construction item: Peace Square Zone; Statue garden; Thrilling game parks, recreation areas for children; Tourist service zone; Downtown; River travel harbor; Internal roads and parking areas, ...

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Entertainment - Public service

Project name: Public service zone

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 5.23 ha

  1. Project objective: The project is located at Nguyễn Xiển and South of the Park road intersection, convenient for transportation and not affecting operations in the Park. The project includes commercial area, food and beverage service area, indoor refreshment and entertainment areas, ... to serve and meet daily needs of visitors to the Park and local residents.

  1. The expected investment capital: VND 100 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 20%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 05 floors



  • Construction item: Includes commercial buildings (shopping, marketing, introduction of cultural products, tourism products, traditional products, local products to visitors), dining area, entertainment area; Parking lot,…

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Culture - History

Project name: Mineral spring tourism flower village

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 16.51 ha

  1. Project objective: The project is located East of the Park, one side adjacent to Đồng Nai River, the rest contiguous to Nguyễn Xiển street (Ring Road 3 in the future). The flower village is where to grow, produce, display and trade all kinds of traditional and modern flowers and ornamental fish; to host exhibition, seminars, training sessions and exchanges to support the movement of cultivating bonsai and transfer of technology to produce ornamental fish and flower, and ornamental plant. In addition, to create the diversity and abundance for recreation and resting in the History - Ethnic Culture Park, the mineral spring resort is where to provide the visitors with services of offset bathing, hot mineral spring, nursing, physiotherapy ... Once formed, this resort is the first to exploit this type of services in Hồ Chí Minh City.

  1. The expected investment capital: VND 400 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 20%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 05 floors



  • Construction item: The flower village includes several central buildings, tea zone, seed bank, artist clubs, nursery and ancillary works, shops, Kiosks, ...; the mineral spring resort includes works of reception area, administrative area, physiotherapy, pool area (mineral pool spa, pool for children, pool for training and hot and cold waterfall), mud bathing area, premium area, restaurants, resorts and other ancillary works, ...

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Business service

Project name: low-rise resort buildings

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 8.06 ha

  1. Project objective: The project is located East of the land plot, next to Đồng Nai River, uses the riverbank position to create landscape on the river, very favorable for yacht service, resort, ... This area has low building density, creates more green space and sports works serving the residential area. This zone is considered the place of rest, recuperation ideal for visitors to have fun, entertainment and stay at the Park with many relaxing services, utilities.

  1. The expected investment capital: VND 500 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 30%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 04 floors



  • Construction item: Low-rise riverside rest houses, swimming pools, sports grounds, sports works to serve residential areas, ....

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Business service

Project name: Cable car - riverside cuisine area

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 3.17 ha

  1. Project objective: The project is located on both sides of Nguyễn Xiển street (Ring Road 3 in the future) and near Đồng Nai River, so it is very convenient for transportation with open space, very convenient for travel services, shopping, dining, sports, ...

  1. The expected investment capital: VND 130 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 20%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 02 floors



  • Construction item: Cable car system area, souvenir stores, convenience stores; Riverside dining areas; Central operating area; Sports and gym area; Resort; Green isolation zone; Technical infrastructure area, parking lot, ...

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):






  1. Project type: Culture - History

Project name: Flower garden area

(Zone IV - Cultural Activity Area of the History - Ethnic Culture Park)



  1. Location: History - Ethnic Culture Park

Long Bình Ward, District 9, Hồ Chí Minh City

  1. Total land area: 5.53 ha

  1. Project objective: The project is located South of the Park, is the area combined with the landscape of Bửu Long Pagoda, separated from the land of Vietnamese Ethnic Culture Village with various types of flowers, ornamental plants, pavilions, ponds, services for tourists, ...

  1. The expected investment capital: VND 100 billion

  1. General information on the project:

  • According to the Decision No. 687/QD-UBND dated 21/02/2009 of People's Committee of Hồ Chí Minh City on approving the project of adjusting the construction planning, scale: 1/2000 of the History - Ethnic Culture Park

  • According to the Decision No. 2485/SQHKT-QHC dated 20/06/2016 of the Department of Planning - Architecture on adding the land use functions and adjusting planning - architectural targets in Zone IV - History - Ethnic Culture Park, Long Bình ward, District 9, Hồ Chí Minh City.

+ Building density: 10%

+ Density of trees, water: 60 -75%

+ Main traffic and yard density: 15 -20%

+ Minimum - maximum construction height: 01 floor



  • Construction item: planting flowers, ornamental plants, pavilions, ponds, services for tourists, ...

  1. Form of investment:

- BOT, BCC, ... and other forms as proposed by the investors.

  1. Contact: History - Ethnic Culture Park Management Board

  1. Notes (schedule, status):



Каталог: HoatDongAnh
HoatDongAnh -> ĐỀ CƯƠng báo cáo kết quả ĐÓng góP Ý kiến của nhân dâN ĐỐi với dự thảo bộ luật dân sự (SỬA ĐỔI) A. NỘi dung chính của báo cáO
HoatDongAnh -> Ủy ban thưỜng vụ quốc hội chính phủ ĐOÀn chủ TỊch ủy ban trung ưƠNG
HoatDongAnh -> Ủy ban nhân dân cộng hòa xã HỘi chủ nghĩa việt nam thành phố HỒ chí minh độc lập Tự do Hạnh phúc
HoatDongAnh -> Ủy ban nhân dân thành phố HỒ chí minh
HoatDongAnh -> Ban thưỜng trực số: 03 /hd-mttq-btt cộng hòa xã HỘi chủ nghĩa việt nam
HoatDongAnh -> CỘng hòa xã HỘi chủ nghĩa việt nam độc lập –Tự do – Hạnh phúc
HoatDongAnh -> Ủy ban nhân dân cộng hòa xã HỘi chủ nghĩa việt nam thành phố HỒ chí minh độc lập Tự do Hạnh phúc
HoatDongAnh -> Ủy ban nhân dân thành phố HỒ chí minh
HoatDongAnh -> QuyếT ĐỊnh về việc ban hành Quy định cơ chế quản lý đầu tư và xây dựng, quản lý nguồn vốn đầu tư tại các xã thực hiện Chương trình
HoatDongAnh -> Ủy ban nhân dân cộng hòa xã HỘi chủ nghĩa việt nam

tải về 3.07 Mb.

Chia sẻ với bạn bè của bạn:
1   ...   5   6   7   8   9   10   11   12   13




Cơ sở dữ liệu được bảo vệ bởi bản quyền ©hocday.com 2024
được sử dụng cho việc quản lý

    Quê hương