Part A – Vessel Personnel and Details
In the First Instance Please Contact the Project Manager
IN COMMERCIAL CONFIDENCE
|
[Name]:
|
Office Phone Number:
|
Mobile Phone Number:
|
E-Mail:
|
Patrick Chan
|
+65 6513 1302
|
+65 9368 9665
|
Patrick.Chan@globalmarine.asia
|
Vessel:
|
CS Cable Retriever / XT601
|
Daily Report No:
|
10
|
Vessel Master :
|
W. Ellis
|
Project:
|
AAE S1H1
|
Vessel Master [E-mail]:
|
Master@retriever.
globalmarine.co.uk
|
Operation:
|
5
|
|
|
Date:
|
07th July 2021
|
Time:
|
08:00 (GMT +8)
|
Chief Engineer :
|
L. Lefterov
|
Position:
|
08º 53.9 N 108º 06.4 E
|
2nd Engineer :
|
L. Whitehead
|
Location:
|
|
Chief Cable Engineer :
|
R. Coles
|
Next Port of Call:
|
Subic Bay, Philippines
|
Chief Subsea Engineer:
|
M. Dale
|
ETA:
|
TBA
|
Ship Superintendent :
|
J. Breckenridge
|
Duration of Stay:
|
TBA
|
Next Bunkering Operation [Anticipated or Known]:
|
Date:
|
Port:
|
Quantity [MT]:
|
|
|
|
Daily Report for 24 Hour Period Ending:
|
See Date and Time above.
|
Distribution of Daily Report
|
Core Daily Report Group and Distribution List Recipients
|
LOCAL AGENT DETAILS:
|
C/O Ben Line Agencies Viet Nam
180-192 Nguyen Cong Tru Street,
Nguyen Thai Binh Ward,
District 1,
Ho Chi Minh City,
Vietnam.
T: +84 28 3825 6148 Ext.: 134
F: +84 28 3823 9097
M: +84 918 264 823
email: offshore@benline.com.vn
|
Part B – Vessel Contact Numbers
1
|
Landlines:
|
|
3
|
V SAT:
|
|
|
Gangway
|
+63(0)47 250 2200
(in Subic)
|
|
Aft Bridge Phone
|
+44 2030 512824
|
|
|
|
|
Test room/Fwd. Bridge Phone
|
+1 954 883 2612
|
|
|
|
|
|
|
|
|
|
|
|
|
2
|
Mobiles:
|
When in range
|
4
|
Fleet broad band:
|
|
|
Captain, Philippines only
|
+63 (0) 917 854 4911
|
|
Aft Bridge Phone
|
+870773992334
|
|
Duty Officer
|
+63 (0) 919 327 4940
|
|
Aft Bridge Fax
|
+870783991031
|
|
Chief Engineer
|
+63 (0) 920 527 0613
|
|
Captain’s Cabin
|
+870773801801
|
Part C – Vessel Daily Report Agenda Items
AA WEATHER
Time GMT(+8)
|
Wind
|
Sea State
|
Swell
|
12:00
|
SW 5
|
4
|
WSW 1.5
|
20:00
|
WSW 6
|
5
|
WSW 2.5
|
02:00
|
WSW 5/6
|
5
|
SW3
|
08:00
|
WSW 6
|
5
|
SW 2
|
BB JOB PERFORMANCE SUMMARY
Activity
|
Brought Fwd
|
Last 24Hrs
|
Cumulative
|
Mobilisation/Demobilisation
|
0.0
|
0.0
|
0.0
|
Depot turnovers
|
0.0
|
0.0
|
0.0
|
Awaiting Permits
|
0.0
|
0.0
|
0.0
|
On Passage
|
88.8
|
0.0
|
88.8
|
At Anchor Clearing In/Out
|
0.0
|
0.0
|
0.0
|
Standby Port
|
0.0
|
0.0
|
0.0
|
Standby Sea
|
0.0
|
0.0
|
0.0
|
At Sea Trials
|
0.0
|
0.0
|
0.0
|
Standby Bunkering
|
0.0
|
0.0
|
0.0
|
Loading Cable and Plant
|
49.0
|
0.0
|
49.0
|
Vessel turnovers
|
0.0
|
0.0
|
0.0
|
Discharge Cable and Plant
|
0.0
|
0.0
|
0.0
|
Rigging/De-rigging.
|
1.0
|
0.0
|
1.0
|
At Sea Cable Work
|
47.3
|
24.0
|
71.3
|
Downtime:- Weather
|
0.0
|
0.0
|
0.0
|
Vessel
|
0.0
|
0.0
|
0.0
|
Other (ROV)
|
0.0
|
0.0
|
0.0
|
Vessel Maintenance Time
|
0.0
|
0.0
|
0.0
|
ROV Maintenance Time
|
0.0
|
0.0
|
0.0
|
|
0.0
|
0.0
|
0.0
|
|
|
|
|
Totals
|
186.1
|
24
|
210.1
|
B1 PROGRESS IN PAST 24 HOURS
Complete First splice RETR/025/21.
Lay in stock cable.
Commence Final splice RETR/026/21 (PGU).
B3 LOOK AHEAD 24 - 48 HOURS
Complete Final splice RETR/026/21 (PGU).
Commence PRIB operations.
B4 ESTIMATED COMPLETION
As per POW
CC 24-HOUR LOG (All times GMT+8 unless otherwise stated)
Tuesday 6th July
08:00 Continue construction of First splice RETR/025/21.
09:14 Mould complete. Commence X-rays
09:57 X-rays complete. Commence X-ray assessment.
10:29 X-ray assessment complete, X-rays passed.
10:41 Commence joint closure.
11:41 First splice RETR/025/21 complete. Prepare to deploy first joint
12:14 CPO First Splice.
Vessel Position: 08 54.0115N 108 06.5673E KP: 2,021.560 km DOW: 75 m
Port Counter: -0.323 km Port Tension: 3.200 kN
12:29 Cable at stern.
Vessel Position: 08 53.9768N 108 06.5067E KP: 2,021.686 km DOW: 75 m
Port Counter: -0.206 km Port Tension: 2.339 kN
12:29 RETR/025/21 at stern.
Vessel Position: 08 53.9750N 108 06.5028E KP: 2,021.690 km DOW: 75 m
Port Counter: -0.109 km Port Tension: 1.649 kN
12:46 Stop PU & PO. Commenced testing of the cable before cutting stock cable.
Vessel Position: 08 53.9399N 108 06.4429E KP: 2,022.209 km DOW: 75 m
Port Counter: 0.135 km Port Tension: 1.742 kN
13:18 PSM RETR/DGB/05
PSM sent to Hong Kong requesting an open circuit condition
14:30 PSM DGB/RETR/05
PSM received from HK confirming open circuit condition.
15:24 PSM RETR/DGB/06
PSM sent requesting HK provide a short circuit condition
15:45 PSM DGB/RETR/06
PSM received confirming short condition at HK terminal.
15:45 Testing of the VTU-BU and Hong Kong cable ends completed satisfactory. Prepare to start final splice setup.
Tests towards Hong Kong before cutting the stock
All fibres clear to repeater S1H1R020
+10mA CR = 3066Ω
-10mA CR = over range
PEFL clear to repeater S1H1R020
IC = 176µF
IR 500V for 10 minutes = 248 MΩ improving
Tests towards VTU-BU before final splice setup.
Fibres White, Blue, Grey and Violet are clear 1.320km to branching unit
Yellow, Brown, Green and Red had light on which prevented testing.
+10mA CR = 105Ω
-10mA CR = 105Ω
PEFL clear to BU at 1.333km @ 97 m/µS
16:19 Commence final splice setup.
Vessel Position: 08 53.9479N 108 06.4571E KP: 2,021.731 km DOW: 68 m
Port Counter: 0.102 km Port Tension: 3.408 kN
16:41 Stock cable cut.
Vessel Position: 08 53.9507N 108 06.4620E KP: 2,021.726 km DOW: 74 m
Port Counter: 0.094 km Port Tension: 0.341 kN
16:56 Final splice setup completed. Prepare to commence final splice RETR026/21.
Vessel Position: 08 53.9510N 108 06.4621E KP: 2,021.726 km DOW: 74 m
Port Counter: 0.102 km Port Tension: 2.801 kN
17:58 Commenced final splice RETR/026/21
22:09 Complete end preparations. Commence ferrule pressing.
23:30 Ferrule pressing complete.
Wednesday 7th July
03:40 Commence fibre splicing.
04:26 Complete fibre splicing. Commence fibre wrapping.
05:10 PSM RETR/DGB/07/VTU/03/SKA/03/SHV/03.
Requesting post splice and wrap system testing is carried out on AAE-1 Segment S1H1.
08:00 Continue with terminal testing.