No.
|
Projects’ names
|
Location
|
Scale
|
Duration for construction of phase I
|
Note
|
1
|
Expansion of K130 terminal (Petrolimex)
|
Quang Ninh
|
250,000 m3
Phase 1: 72,000 m3
Phase 2: 180,000 m3
|
2008-2009
(2009-2014)
|
Imported by pipeline from Bai Chay terminal
|
2
|
Expansion of K131 terminal (Petrolimex)
|
Thuy Nguyen-Hai Phong
|
60,000 m3
Phase 1: 40,000 m3
|
2009-2010
|
Received by B12 pipeline
|
3
|
New construction of terminal K132 (Petrolimex)
|
Hai Duong
|
100,000 m3
Phase 1: 50,000 m3
|
2009-2011
|
Received by B12 pipeline
|
4
|
New construction of Ha Nam terminal (Petrolimex)
|
Ha Nam
|
60,000 m3
Phase 1: 20,000 m3
|
2008-2010
|
Received by B12 pipeline
|
5
|
New Dinh Vu – VIPCO terminal (Petrolimex)
|
Hai Phong
|
Phase 1: 150,000 m3
|
2009-2012
|
It has had agreement of ports with Ministry of Transport
|
6
|
New construction of Phu Xuyen terminal - (Petrolimex)
|
Phu Xuyen-Ha Noi
|
100,000 m3
Phase 1: 60,000 m3
|
2010-2012
|
Received by B12 pipeline
|
7
|
New construction of Phu Thi terminal (Petrolimex)
|
Gia Lam – Ha Noi (or Thuan Thanh – Bac Ninh)
|
120,000 m3
Phase 1: 60,000 m3
|
2011-2015
|
Received by B12 pipeline
|
8
|
New construction of Lach Huyen depot (Petrolimex/PV Oil and other enterprises)
|
Lach Huyen – Bac Ninh
|
Up to 500,000 m3
Phase 1: 200,000 m3
|
2010-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
9
|
Expansion of Thuong Ly depot
|
Thuong Ly – Hai Phong
|
40,000 m3
|
2010-2012
|
Received by B12 pipeline
|
10
|
Expansion of Dinh Vu terminal (PV Oil)
|
Hai Phong
|
30,000 m3
|
2008-2009
|
Using Dinh Vu oil Port
|
11
|
New construction of Vinashin depot
|
Dam Nha Mac – Quang Ninh
|
Up to 200,000 m3
Phase 1: 100,000 m3
|
2010-2012
|
It needs to have a agreement of ports with Ministry of Transport
|
12
|
New construction of Vinapco Hai Phong terminal
|
Hai Phong
|
50,000 m3
|
2010-2015
|
Using Dinh Vu oil Port
|
13
|
New construction of Dinh Vu terminal (Vitranchart)
|
Hai Phong
|
20,000 m3
Phase 1: 10,000 m3
|
2010-2012
|
It needs to have a agreement of ports with Ministry of Transport
|
14
|
Expansion of Cai Lan terminal (PV Oil)
|
Quang Ninh
|
Up to 70,000 m3
|
2009-2012
|
It needs to have a agreement of ports with Ministry of Transport
|
15
|
Expansion of Viet tri terminal (Petrolimex)
|
Viet Tri – Phu Tho
|
20,000 m3
|
2009-2012
|
It has had river port
|
16
|
New construction of Vung Ang terminal (PV Oil)
|
Ha Tinh
|
100,000 m3
Phase 1: 60,000 m3
|
2008-2009
|
It has had agreement of ports with Ministry of Transport
|
17
|
New construction of Hon La terminal (PV Oil)
|
Hon La port – Quang Binh
|
100,000 m3
Phase 1: 40,000 m3
|
2011-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
18
|
Expansion of Cua Viet terminal
|
Quang Tri
|
Up to 20,000 m3
|
2010-2012
|
It needs to have a agreement of ports with Ministry of Transport
|
19
|
Expansion of Chan May terminal (PV Oil)
|
Chan May port, Thua Thien Hue
|
Up to 50,000 m3
Phase 1: 25,000 m3
|
2009-2010
|
Has had port
|
20
|
New construction of Tho Quang terminal (Petrolimex)
|
Da Nang
|
90,000 m3
Phase 1: 40,000 m3
|
2009-2013
|
It needs to have a agreement of ports with Ministry of Transport
|
21
|
Expansion of Lien Chieu terminal (PV Oil)
|
Da Nang
|
Up to 30,000 m3
|
2009-2011
|
Has had port
|
22
|
New construction of Da Nang terminal (PV Oil)
|
Da Nang
|
Up to 50,000 m3
Phase 1: 25,000 m3
|
2010-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
23
|
Expansion of Phu Hoa terminal (Petrolimex)
|
Binh Dinh
|
50,000 m3
|
2009-2015
|
Has had port
|
24
|
New construction of Van Phong bonded terminal (Petrolimex)
|
Khanh Hoa
|
1,000,000 m3
Phase 1: 500,000 m3
|
2009-2012
|
It has had agreement of ports with Ministry of Transport
|
25
|
Expansion of Vung Ro terminal (VTTH Phu Yen Company)
|
Phu Yen
|
40,000 m3
|
2009-2015
|
Has had port
|
26
|
New construction of Southern Central terminal (Petrolimex)
|
Ninh Thuan or Binh Thuan
|
50,000 m3
|
2010-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
27
|
New construction, expansion of B, C terminals, Nha Be depot (Petrolimex)
|
Ho Chi Minh City
|
280,000 m3
|
2008-2015
|
Has had port
|
28
|
New construction, expansion of D, E terminals, Nha Be depot (Petrolimex)
|
Ho Chi Minh City
|
Up to 400,000 m3
Phase D terminal: 120,000 m3
|
2009-2020
|
Has had port
|
29
|
Expansion of Nha Be depot (PV Oil)
|
Ho Chi Minh City
|
Up to 130,000 m3
Phase 1: 50,000 m3
|
2008-2009
|
Has had port
|
30
|
New construction of Nha Be terminal (Vinapco)
|
Ho Chi Minh City
|
Up to 200,000 m3
Phase 1: 50,000 m3
|
2010-2015
|
Has had port
|
31
|
New construction of Cu Lao Tao terminal (PV Oil)
|
Ba Ria – Vung Tau
|
Phase 1: 150,000 m3
Phase 2: 150,000 m3
|
2007-2009
2011-2015
|
It has had agreement of ports with Ministry of Transport
|
32
|
New construction of Cai Mep depot (Petec – PV Oil)
|
Ba Ria – Vung Tau
|
Up to 150,000 m3
Phase 1: 80,000 m3
|
2009-2011
|
It has had agreement of ports with Ministry of Transport
|
33
|
New construction of XD COMECO depot
|
Nhon Trach – Dong Nai
|
Up to 100,000 m3
Phase 1: 44,000 m3
|
2008-2010
|
It has had agreement of ports with Ministry of Transport
|
34
|
New construction of Phu Huu depot (Tin Nghia company)
|
Nhon Trach – Dong Nai
|
Up to 180,000 m3
Phase 1: 60,000 m3
|
2008-2010
|
It has had agreement of ports with Ministry of Transport
|
35
|
New construction of Nhon Trach depot (PV Oil)
|
Nhon Trach – Dong Nai
|
Up to 100,000 m3
|
2012-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
36
|
New construction of sountheast depot (Petrolimex)
|
Dong Nai or Ba Ria Vung Tau
|
Up to 200,000 m3
|
2010-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
37
|
New construction of Soai Rap terminal (PetroMekong PV Oil)
|
Go Cong Dong – Tien Giang
|
Up to 520,000 m3
Phase 1: 160,000 m3
|
2008-2010
|
It needs to have a agreement of ports with Ministry of Transport
|
38
|
New construction of Soai Rap terminal (Thuan Tien company)
|
Go Cong Dong – Tien Giang
|
Up to 110,000 m3
Phase 1: 60,000 m3
|
2010-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
39
|
New construction of Vinh Long terminal
|
Vinh Long township –Vinh Long province
|
20,000 m3
|
2010-2015
|
Riverport, it needs to have a agreement with Department of Waterway
|
40
|
New construction of Long Binh Tan transshipment terminal (Petrolimex)
|
Dong Nai
|
Up to 50,000 m3
Phase 1: 20,000 m3
|
2010-2015
|
Riverport, it needs to have a agreement with Department of Waterway
|
41
|
Expansion of Can Tho terminal (PV Oil)
|
Tra Noc Industrial zone – Can Tho
|
60,000 m3
Phase 1: 40,000 m3
|
2008-2010
|
It has had agreement of ports with Ministry of Transport
|
42
|
Expansion of Can Tho terminal (PetroMekong)
|
Cai Rang District – Can Tho City
|
36,000 m3
|
2008-2009
|
Has had port
|
43
|
New construction of Ca Mau terminal (PV Oil)
|
Ca Mau
|
Up to 11,000 m3
|
2008-2010
|
It needs to have a agreement of ports with Ministry of Transport
|
44
|
New construction of Tra Vinh terminal (CAWACO)
|
Kim Son – Tra Cu Tra Vinh
|
Up to 200,000 m3
Phase 1: 100,000 m3
|
2010-2015
|
It needs to have a agreement of ports with Ministry of Transport
|
45
|
New construction of Kien Luong terminal (PV Oil)
|
Kien Luong – Kien Giang
|
Up to 100,000 m3
|
2010-2013
|
It needs to have a agreement of ports with Ministry of Transport
|
46
|
New construction of Kien Luong terminal (Petrolimex)
|
Kien Luong – Kien Giang
|
Up to 100,000 m3
Phase 1: 30,000 m3
|
2010-2012
|
It needs to have a agreement of ports with Ministry of Transport
|
47
|
New construction and expansion of jet fuel depots Jet A1
|
In the airports: Noi Bai, Da Nang, Cat Bi, Phu Cat, Phu Xuan, Cam Ranh
|
10,000 -15,000 m3/each location
|
2010-2020
|
Imported by road tanker
|
48
|
Expension of Phu My terminal – Condensate processing factory
|
Cai Mep industrial zone, Tan Thanh, Ba Ria-Vung Tau province
|
Up to 75,000 m3
|
2008-2010
|
|
49
|
New construction of Dung Quat – PV Oil terminal (hub reserve or for factory expansion)
|
Quang Ngai
|
Up to 1,000,000m3
Phase1: 500,000 m3
|
2010-2015
|
|